PM Dr. RALPH GONSALVES
PM Dr. RALPH GONSALVES

Gov’t allocates EC$74.7 million to complete airport

By Admin Wednesday February 04 2015 in Caribbean
COMMENTS
1 Star2 Stars3 Stars4 Stars5 Stars (No Ratings Yet)
Loading ... Loading ...


 

KINGSTOWN: The Government of St. Vincent & the Grenadines has allocated EC$74.7 million (one EC dollar=US$0.37 cents) towards the completion of the Argyle International Airport.

 

St. Vincent & the Grenadines Prime Minister Dr. Ralph Gonsalves said the EC$729 million airport has missed several completion deadlines, the most recent in December of last year.

 

However, Dr. Gonsalves told Parliament it “will be completed this year and ready for operation”.

 

Gonsalves, who is also Minister of Finance, said a portion of the EC$74.7 million is the remainder of the US$9.5 million (EC$25.6 million) outstanding on the US$20 million sale of lands to developers in the southern Grenadine island of Canouan.

 

He said he has been reliably advised that the money would be paid within six weeks.

 

Gonsalves said that delays in the timely receipt by the International Airport Development Company (IADC) — the state-owned firm responsible for building the airport — of negotiated resources and excessively inclement weather have hampered the pace of construction of the airport.

 

The government had said that the airport would have been “substantially complete” at the end of 2014.

 

“As always, our government makes contingency plans in the event of the delay in the draw-down of grants or soft-loans,” he said. “This has been a constant factor in the life of the airport’s construction.”

 

He told Parliament that the earthworks are 97 per cent complete, and the remainder of the work “will be carried out without any real inconvenience to the parallel Airside Works”. The earthwork is scheduled to be completed by the end of March.

 

The Yambou River runs across the runway, and Gonsalves said that work on the drainage system to accommodate this waterway is programmed for completion by the end of April to allow for the asphalt pavement works on that section of the runway to be done.

 

He said the ongoing work on other drainage systems continued during 2014 and are substantially advanced and programmed to be completed in the first quarter of this year.

 

“The pavement works have already commenced with the placement of the base and sub-base for the runway, aprons and taxiways. “The asphalt pavement works and the concrete works on the aerodrome are programmed to be completed by the end of May 2015.

 

“And the wind studies continue; data show, thus far, no crosswind sufficient to affect the safe operation of the Argyle Airport for the smallest of aeroplanes, that is, those whose reference field length is less than 1,200 metres. In the first half of 2015, the IADC will again provide all the up-to-date win data and analysis for public information,” said Gonsalves.

 

The Prime Minister said that marketing of the airport is continuing.

 

“Several airlines have expressed interest in adding St. Vincent and the Grenadines to their routes,” he said. “Air services agreements are expected in the first half of 2015 with several of them.”